Interpreting Practical Completion: University of Warwick v Balfour Beatty Group [2018] EWHC 3230 (TCC)

Background: The University of Warwick (Warwick) contracted Balfour Beatty Group Ltd (Balfour Beatty) under an amended JCT 2011 D&B to design and construct the National Automotive Innovation Centre (the Centre). The works were split into 4 sections. Balfour Beatty took possession of each of these sections on the 20 April 2015. However, the dates for…

Continue reading