The Court of Appeal’s decision in Triple Point Technology v PTT [2019] EWCA Civ 230 has cast some doubt on the decision in last year’s case of GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866, which had accepted that liquidated damages clauses may continue to accrue beyond contract termination.